Construction Projects

Project Name Location Estimated Completion Detour Information Latest Updates

Garner Creek Stream Restoration Phase 1

998 Cole Drive
Lilburn, GA 30047

Adjacent to Parkview High School and Gwinnett Soccer Association

Fall/Winter 2019 Ephemeral Lane Closures

Early phase of construction.  No major traffic delays anticipated throughout the duration of the project.

Phase 1 stream restoration of Garner Creek with EPA special appropriations grant.  Construction grade stakes, barrier fences, erosion control measures, and contractor mobilization currently phased.

Grayson New Hope Along Grayson New Hope Road, extending from the intersection with New Hope Road in the north, to approximately ½ a mile south of the intersection with Chandler Road (the location of the Grayson Water Tank) in the south. Summer 2019 View Detour Here A public meeting will be held on May 28, 2019 for residents to discuss phase 2 of ths project, which will extend to Brannan Road. The meeting will be held at the Grayson Senior Center, 475 Grayson Parkway, between the hours of 6:30pm and 7:30pm.

The road is accessible to local businesses during construction. 

Beginning May 28, 2019, traffic the detour will be changing.  Follow detour signs to Buck Jones Nursery and Brookside Kennel. 

The updated estimated completion date for phase 1 is June, 2019.
Old Norcross Road Bridge Replacement with Culvert Installation Old Norcross Road Bridge near Atlanta Korean Seventh Day Adventist Church   View Detour Here

Scheduled to begin May 23, 2019.

Mountain Park Elementary Sewer Project  The project is located near Mountain Park Elementary School, along Brownlee Road SW, Southern Pine Way SW, and Puckett Drive.  August 2019  

Sections of Brownlee Road SW, Southern Pine Way SW, and Puckett Drive are scheduled to temporarily close to through-traffic from May 23, 2019 to August 5, 2019. Access to local residences will be available throughout construction.

Pharr Woodberry GS Extension The project will run from the Pharr Elementary Pump Station southward, through Georgetown Way, a section of Natchez Way, Winding Creek Circle, Brookstone, a section of Pharr Road, make an immediate right turn onto Lakeview Road. Summer 2019 Intermittent Lane Closures Tentative Blasting Schedule

The contractor will be placing sod on properties that have complete sewer cleanouts. Curb and gutter is being replaced along a section of Winding Creek Circle. Blasting is scheduled for May 22, 2019. 

Project Manager Peter Coker at 678.376.6991 or the Project Inspector Anthony Hogan at 678.376.7060. 

Find out the steps to switch from septic to sewer here
Sunny Hill Sunny Hill Road between Old Peachtree Road and Gravel Springs Road Fall 2019 View Detour Here  The intersection of Sunny Hill Road and Old Peachtree Road is now open, however Sunny Hill Road is closed between Old Peachtree Road and Gravel Springs Road.