Construction Projects

Project Name Location Estimated Completion Detour Information Latest Updates

Haynes Club Circle

This project is located at Haynes Club Way. Late November/Early December 2019  The detour route will be Haynes Club Circle to Haynes Club Way to Haynes Club Circle and the reverse. The project is for the purpose of drainage improvements. For further information contact Water Resources at 678.376.6983

Bailey Road Water Main Installation

Dacula, GA 
Wages Road to Union Grove Road
Summer 2020   Bailey Road will experience intermittent lane closure from December 2, 2019 to June 2020.

Garner Creek Stream Restoration Phase 1

998 Cole Drive
Lilburn, GA 30047

Adjacent to Parkview High School and Gwinnett Soccer Association

Fall/Winter 2019 Ephemeral Lane Closures

Major construction measures are complete and contractor is in punch-list phase.

Minor work to be completed by December 15, and no major traffic delays anticipated. Garner Creek Stream Restoration Phase 2 Green-Infrastructure BMPs anticipated to begin in early 2020. Please check back for Phase 2 updates. 

Grayson New Hope Road 48" Main Replacement The first phase of this project is located along Grayson New Hope Road between New Hope and Chandler Road. 

The second phase of this project is located along Grayson New Hope between Chandler Road and Brannan Road, down Brannan Boulevard, and a small section of Herring Road between Brannan Boulevard and Loganville Highway. 
June 2020 Phase two (from Chandler to Round Road) Detour: Grayson New Hope to Round Road to Chandler to Grayson New Hope and the reverse.

Grayson New Hope is closed from Grayfield subdivision to Brannan Boulevard. This is scheduled to re-open on December 23rd.

McConnell Road is closed until December 13th from Leighs Grove Way to Grayson New Hope Road.

Brannan Boulevard is expected to close to all through traffic beginning mid-December through early February, those dates have not been officially and are subject to change. 

Estimated completion for phase two of this project is June, 2020.

Project Manager: Michael Efeyini at 678.376.7069

Paper Mill Road/Shoal Creek Interceptor

Easements east of Paper Mill Road Late Summer 2020  

Project will add a sewer line in the vicinity of Paper Mill Road and Shoal Creek.

Pharr Woodberry GS Extension The project will run from the Pharr Elementary Pump Station southward, through Georgetown Way, a section of Natchez Way, Winding Creek Circle, Brookstone, a section of Pharr Road, make an immediate right turn onto Lakeview Road. January 2020 Intermittent Lane Closures Restoration work continues. Paving will begin in Northforke Plantation on December 10th.

Project Manager Chad Horner at 678.376.6940 or the Project Inspector Anthony Hogan at 678.376.7060. 

How to connect to sewer if you live in unincorporated Gwinnett

How to connect to Sewer if you live in the city of Snellville

Additional Information About Connecting To Sewer
Sunny Hill Sunny Hill Road between Old Peachtree Road and Gravel Springs Road January 2020 View Detour Here Both schools in the area are now accessible from multiple directions. Blasting may occur in the area.

Project Manager: Michael Efeyini at 678.376.7069