Construction Projects

Project Name Location Estimated Completion Detour Information Latest Updates

Burns Road Drainage Improvement

This project is located at 3926 Burns Road in Lilburn, near the intersection of Pleasant Hill Road.

 June 2019 View Detour Here

Burns Road is now open to traffic.

This project is expected to begin on June 3, 2019 and is scheduled to be completed by early July.

Project Manager: Justin Grier at 678.376.6983

Dawson Boulevard drainage improvements

 6948 Dawson Boulevard, near the intersection of Warren Drive.


 July 3, 2019  Lane shift  Lanes will be shifted starting 6/20 

Garner Creek Stream Restoration Phase 1

998 Cole Drive
Lilburn, GA 30047

Adjacent to Parkview High School and Gwinnett Soccer Association

Fall/Winter 2019 Ephemeral Lane Closures

Mid-phase of construction.  No major traffic delays anticipated throughout the duration of the project.

Upper and middle sections of major grading are complete. Contractor will continue to maintain erosion control measures and will complete all plantings in the fall.

Grayson New Hope Road 48" Main Replacement The first phase of this project is located along Grayson New Hope Road between New Hope and Chandler Road. 

The second phase of this project is located along Grayson New Hope between Chandler Road and Brannan Road, down Brannan Boulevard, and a small section of Herring Road between Brannan Boulevard and Loganville Highway. 
Summer 2019 Phase one (from North Round Road to New Hope Road) Detour: Grayson New Hope Road to Chandler Road to Bowman Road to New Hope Road to Grayson New Hope Road and the reverse.

Phase two (from Chandler to Round Road) Detour: Grayson New Hope to Round Road to Chandler to Grayson New Hope and the reverse.
The contractor is finishing up work on the first phase of this project. Grayson New Hope is closed to through traffic from New Hope to Meyers Drive and  between Round Road and Chandler Road. This section is expected to be completed July 22, 2019.

Beginning June 10, 2019, installation of the 12" water main will begin near Round Road. After the 12" main is installed, the contractor will begin installing the 48" main.

Estimated completion for phase two of this project is June, 2020.

Project Manager: Michael Efeyini at 678.376.7069
Old Norcross Road Bridge Replacement with Culvert Installation Old Norcross Road Bridge near Atlanta Korean Seventh Day Adventist Church   View Detour Here

Work has begun at this project and the detour is in place. Estimated completion is August 2019.

Project Manager: Mark Lawrence at 678.376.6950

Mountain Park Elementary Sewer Project  The project is located near Mountain Park Elementary School, along Brownlee Road SW, Southern Pine Way SW, and Puckett Drive.  August 2019  

Sections of Brownlee Road SW, Southern Pine Way SW, and Puckett Drive are scheduled to temporarily close to through-traffic from May 23, 2019 to August 5, 2019. Access to local residences will be available throughout construction.

Project Manager: Chad Horner at 678.376.6940

Paper Mill Road

 

   June 2019  

 The Gwinnett County Department of Water Resources, in conjunction with a contracted construction company, will be closing a portion of Paper Mill Road between McCart Road and Castlebrook Drive.

Project Manager Peter Coker at 678.376.6991

Pharr Woodberry GS Extension The project will run from the Pharr Elementary Pump Station southward, through Georgetown Way, a section of Natchez Way, Winding Creek Circle, Brookstone, a section of Pharr Road, make an immediate right turn onto Lakeview Road. Summer 2019 Intermittent Lane Closures Restoration work has begun in Williams Manor. 

The pump station is scheduled to be disconnected and demolished in mid-July 2019. 

The contractor has begun working in Northforke.

Project Manager Peter Coker at 678.376.6991 or the Project Inspector Anthony Hogan at 678.376.7060. 

Find out the steps to switch from septic to sewer here
Sunny Hill Sunny Hill Road between Old Peachtree Road and Gravel Springs Road Fall 2019 View Detour Here Sunny Hill Road is closed to through traffic from Lena Carter Road to Field View Drive.

Project Manager: Michael Efeyini at 678.376.7069