Sugarloaf Parkway Extension from State Route 20 / Grayson Highway to State Route 316 / University Parkway
Project Description The new road features two 12-foot lanes in each direction with a 44-foot grassed median and 16-foot shoulders within a 200-foot right-of-way. The speed limit is 45-mph through the first two curves east of SR 20 and then 55-mph for the remaining length of the project. The route includes upgraded, signalized intersections at State Route 20, New Hope Road, Martins Chapel Road, Campbell Road, and a half-cloverleaf interchange at State Route 316.
The Extension crosses over Chandler Road and under Hiram Davis Road and Alcovy Roads. Bramlett Shoals Road on either side of the extension is closed and now consists of a new, two-lane connector road constructed from Hiram Davis Road to Bramlett Shoals Road.
About Sugarloaf Parkway Extension Phase 1 - Section 1
Two-mile extension of Sugarloaf Parkway from State Route 20 to New Hope Road
Project will improve mobility in the central and eastern part of Gwinnett County
Over 1.5 miles of improvements to existing roadways
Four-lane divided, limited-access parkway
Intersection with State Route 20 includes dual left turns and right turn lanes on all approaches
Interchange at Sugarloaf Parkway Extension and New Hope Road
Chandler Road bridge allows local traffic access under Sugarloaf Parkway
Construction costs: approximately $23.5 million
Funded primarily through 2005 Special Purpose Local Option Sales Tax (SPLOST) with a contribution of $2.5 million from the Georgia Department of Transportation
Construction began December 2007
55,000 tons of asphalt placed
98,000 tons of rock base placed
11,000 feet of storm drain pipe installed
14,000 feet of guardrail installed
About Sugarloaf Parkway Extension Phase 1 - Section 2
1.4 mile extension of Sugarloaf Parkway from New Hope Road to Martins Chapel Road
Project will improve mobility in the central and eastern part of Gwinnett County
Approximately 0.86 miles of improvements to existing roadways
New 0.5 mile two lane connector road ties Bramlett Shoals Road to Martins Chapel Road north of Sugarloaf Parkway
4 lane divided limited access parkway
Interchange at Sugarloaf Parkway Extension and Martins Chapel Road
Hiram Davis Road bridge allows local traffic access over Sugarloaf Parkway
Construction contract in the amount of approximately $24.8 million awarded December 2008
Funded primarily through 2009 Special Purpose Local Option Sales Tax with a contribution of $2.5 million from the Georgia Department of Transportation
Project opened to traffic December 14, 2010
26,000 tons of asphalt placed
56,000 tons of rock base placed
3,500 feet of storm drain pipe installed
1,700 feet of guardrail installed
About Sugarloaf Parkway Extension Phase 1 – Section 3A
2.3 mile extension of Sugarloaf Parkway from Martins Chapel Road to West Campbell Road
Project will improve mobility in the central and eastern part of Gwinnett County
Over 0.48 miles of improvements to existing roadways
New 0.5 mile two lane connector road ties Bramlett Shoals Road to Martins Chapel Road north of Sugarloaf Parkway
4 lane divided limited access parkway with 44 foot depressed median
Includes new bridge over Alcovy River
Interchange at Sugarloaf Parkway Extension and West Campbell Road
Construction contract in the amount of approximately $15.5 million awarded December 2009
Funded primarily through 2009 Special Purpose Local Option Sales Tax
Project opened to traffic August 2011
35,000 Tons of asphalt placed
58,000 Tons of rock base placed
4,800 Feet of storm drain pipe installed
18,000 Feet of guardrail installed
About Sugarloaf Parkway Extension Phase 1 – Section 3B (from Campbell Road to SR 316 EB)
0.62 mile extension of Sugarloaf Parkway from West Campbell Road to SR 316/University Parkway
0.20 miles of entrance ramp from West Campbell Road to Sugarloaf Parkway NB
0.20 miles of exit ramp from Sugarloaf Parkway SB to West Campbell Road
0.57 miles of entrance ramp from SR 316/University Parkway EB to Sugarloaf Parkway SB
0.59 miles of exit ramp from Sugarloaf Parkway NB to SR 316/University EB
0.59 miles of entrance ramp from Sugarloaf Parkway NB to SR 316/University WB
0.60 miles of exit ramp from SR 316/University Parkway to Sugarloaf Parkway SB
0.47 mile of improvement and horizontal and vertical realignment of Alcovy Road between West Campbell Rd and West Drowning Road
32,097 tons of asphalt placed
59,272 tons of graded aggregate base placed
5,399 feet of storm drain pipe installed
20,050 feet of guardrail installed
13,066 feet pf fence installed
1,550,000 cubic yards of embankment
4,800 linear feet of fiber optic cable installed
Section from West Campbell Road to SR 316 EB opened to traffic on July 2, 2012
Interchange with SR 316/University Parkway opened to traffic on December 11, 2012, completing the entire Phase 1 from SR 20 to SR 316.